Implement Beam hog modeling aligned to Australian Bridge design

Current Beam hog modeling is not as expected for Australian Bridges. Deck thickening can be applied, but the beams that support the deck do not follow the underside shape of the deck. The beams are straight, but really need to be curved and follow...
over 1 year ago in OpenBridge Designer / OpenBridge Modeler 0 Needs review

Template Creation window access ProjectWise datasource to load xml template libraries from another project

Provide a ProjectWise datasource connection to the OBM Template Creation window to open a "Select Document" dialog. The OBM Template Creation window is unable to OPEN another XML from ProjectWise - Open dialog is currently limited to Windows File ...
about 1 year ago in OpenBridge Modeler 0 Needs review

More decoration features for plans production

We need additional 2D decoration feature definitions for better control in plans production, specifically for barrier and drilled shafts
over 1 year ago in OpenBridge Designer / OpenBridge Modeler 0 Needs review

Add a negative function into longitudinal/transverse offsets

Greater flexibility for wingwall placement
almost 2 years ago in Geometry / OpenBridge Designer / OpenBridge Modeler 0 Needs review

Place one bearing at pier location for continuous span concrete girder bridge design

Ability to place only one bearing at pier location for continuous span concrete girder bridge design, two girders shearing one bearing at pier location.
almost 2 years ago in OpenBridge Designer / OpenBridge Modeler 0 Needs review

Modeling horizontal bracing for steel girder bridge

I believe OpenBridge modeler missing function to place horizontal bracing between girders (angle or CHS member) CHS preferable.
almost 2 years ago in OpenBridge Designer / OpenBridge Modeler 0 Needs review

Allow member groups to start and stop at the same support line in LBS

We are modeling a complex bridge in LBS and the bridge is flared. The flare has required the addition of shorter beams that are not full length to keep the beam spacing on the flared end reasonable. Currently LBS does not allow more than one beam ...
over 1 year ago in Modeling / OpenBridge Designer / OpenBridge Modeler 0 Needs review

Bridge centerline

It will be very helpful if OBM can project the deck centerline along the length of the bridge.
over 1 year ago in OpenBridge Designer / OpenBridge Modeler 0 Needs review

Openbridge: add the ability to have curved abutment and or curved retaining wall

Openbridge: add the ability to have curved abutment and or curved retaining wall
about 2 years ago in Modeling / OpenBridge Designer / OpenBridge Modeler 0 Needs review

Allow Pier Diaphragms to fall between the beam ends rather than encasing the beams inside the diaphragm (TDOT).

TDOT doesn't encase the beams inside of the pier diaphragms. TDOT places an 18" diaphragm between the beam ends with bent-up strands being used for anchorage into the diaphragm. If the bridge is skewed, the diaphragms are skewed at a different ang...